The installation of reinforcing bars for concrete construction, or rebar, is a specialized construction activity that is inherently dangerous not only for the craftsmen engaged in the actual rebar…
Jeffrey Tedder is a Civil Engineer with nearly 20 years of professional construction and engineering experience. His experience in complex, industrial construction where all trades are involved has granted Jeff a comprehensive understanding of the construction industry. Jeffrey applies his knowledge of the industry and expertise in standards and best practices to forensic casework involving construction claims and injuries.
Much of Jeff's professional career focused on the development and construction of public works facilities and wastewater treatment plants. His project experience includes new site development, capital improvements on existing facilities, and demolition efforts to make way for new construction. As general contractor he managed sitework, precast and site cast concrete, utilities, and process mechanical work, in addition to managing the efforts of electrical, building architectural, and building mechanical trade subcontractors. Jeff was responsible for site safety, CPM scheduling, quality, change order management, and subcontractor management. He later assumed the role of Engineering Manager and supervised the efforts of a project engineering team where he directed and managed the general contractor's engineering activities for two simultaneous projects on the Patapsco Wastewater Treatment Plant, contracted at $138M.
Jeffrey earned his BS in Civil Engineering from the University of Alabama. He is a licensed Professional Engineer in multiple states and has completed the OSHA-10, -30, and -40 Hour HAZWOPER certification programs. He is a member of the American Society of Civil Engineers (ASCE) Construction Institute.
Heavy/Civil Construction
General Construction
Project Management
Special Projects
Associate
2021 to presentProvide technical investigations, analysis, reports, and testimony toward the resolution of commercial claims and personal injury litigation involving construction practices and construction project management, estimating and scheduling, delay claims, construction site safety practices, quality control and quality assurance, and other civil engineering issues in the heavy, industrial, commercial, and residential construction industries.
Project Manager
2021Project manager in charge of multiple concurrent public works construction projects in various stages of completion in the greater Atlanta area. Responsible for the safety, CPM schedule, quality, and budget for each project. As general contractor, IHC self-performed sitework, utilities, and process mechanical work as well as subcontracted and managed the efforts of deep foundation, concrete, electrical, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical work. Responsibilities included the completion of punch-list and warranty repairs of defective work from previously completed projects.
Project Manager
2018 to 2021Project manager in charge of two concurrent public works construction projects valued at $57 MM in Columbus, GA and Knoxville, TN. Responsible for all aspects of the projects including the safety, CPM schedule, quality, and budget for both projects. As general contractor, Lane self-performed sitework, utilities, and process mechanical work as well as subcontracted and managed the efforts of demolition, deep foundation, concrete, electrical, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical work. Construction operations included the planning, implementation, and management of complex large scale facility bypass operations to maintain plant operation during construction.
Senior Project Manager/Construction Manager 2016-2017
In charge of the construction of a new water treatment plant for the City of Lebanon, OR ($27MM). Responsible for all aspects of the project including the safety, CPM schedule, quality, and budget. As Construction Manager/General Contractor (CM/GC) collaborated with the Engineer of Record and Owner to Value Engineer the project within the Owner’s scope and budget and negotiated the Guaranteed Maximum Price (GMP). Self-performed work included sitework, concrete, utilities, and process mechanical. Subcontracted work included concrete reinforcing, electrical, pre-manufactured metal building, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical. Construction operations included the planning, permitting, implementation, and management of complex installation of an in-river water intake structure. Value Engineered the project from $34MM to $27MM
Pre-Construction Manager 2016
Managed the Builder’s efforts for the Design Build team on a wastewater plant project to assist the City of Klamath Falls, Oregon in developing the project scope. Helped develop the proposal to advance the approx. $35MM project to Phase 1B project design.
Project Manager 2014-2016
Directed and managed the construction activities of the $263 Million Back River WWTP Denitrification Filtration Upgrades project (SC877). Supervised and mentored a staff of (12) including (8) project engineers. Responsible for all aspects of the project including safety, CPM schedule, quality, and budget. Negotiated owner change orders in excess of $12MM and time extension requests of 33 calendar days. As general contractor, Archer Western self-performed sitework, concrete, utilities, and process mechanical work as well as subcontracted and managed the efforts of demolition, deep foundation, concrete reinforcement, electrical, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical work. Construction operations included the excavation of 50,000 CY of earth, the placement of 70,000 CY of concrete, and the installation of large bore buried piping as large as 108 inches in diameter.
Assistant Project Manager 2013-2014
As assistant project manager on the Back River WWTP SC877 project, supervised the efforts of the 8-member project engineering team. Responsible for safety, CPM scheduling, quality, project engineering, and change order management.
Project Manager
2012 to 2013Project Manager in charge of three concurrent public works projects with a combined value of $22 Million within the Baltimore metropolitan area. Responsible for all aspects of the projects including the safety, CPM schedule, quality, project engineering, and budget for the projects. As general contractor, ACE self-performed sitework, utilities, and process mechanical work as well as subcontracted and managed the efforts of deep foundation, concrete, electrical, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical work. ACE also served as the process mechanical subcontractor for The Christman Company on a wastewater upgrade project in Alexandria, VA.
Engineering Manager 2009-2012
Directed and managed the engineering activities for two (2) simultaneous projects (SC 852R & SC 855) on the Patapsco Wastewater Treatment Plant contracted at $138 million. Supervised the efforts of the 5-member project engineering team. Responsible for safety, CPM scheduling, quality, project engineering, and change order management. As general contractor, Fru-Con self-performed sitework, concrete, utilities, and process mechanical work as well as subcontracted and managed the efforts of deep foundation, electrical, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical work.
Mechanical Project Engineer 2007-2009
Project Engineer primarily responsible for management of the process mechanical portion of the $136MM Arlington Wastewater Treatment Plant phase 7A project. Responsible for safety, CPM scheduling, quality, project engineering, change order management, and subcontractor management for the mechanical scope of the project. As general contractor, Fru-Con self-performed sitework, concrete, utilities, and process mechanical work as well as subcontracted and managed the efforts of deep foundation, electrical, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical work.
Project Engineer 2005-2007
Project Engineer responsible for management of the project engineering portion of the $30MM + Kent Narrows wastewater treatment plant project in Stevensville, MD. Responsible for safety, CPM scheduling, quality, project engineering, change order management, and subcontractor management for the project. As general contractor, Fru-Con self-performed sitework, concrete, utilities, and process mechanical work as well as subcontracted and managed the efforts of concrete reinforcement, electrical, building architectural (framing, roofing, finish carpentry, doors, windows, drywall, paint, flooring, finishes, etc.), and building mechanical work.
Land Development Civil Design Engineer
2004Engineer responsible for completing design drawings and other related documentation for various commercial and residential land development projects, and preparation and submission of client documentation for state stormwater permits under the EPA National Pollutant Discharge Elimination Systems (NPDES).
Continuing Education
v. 07/7/22
The installation of reinforcing bars for concrete construction, or rebar, is a specialized construction activity that is inherently dangerous not only for the craftsmen engaged in the actual rebar…
Concrete pumping operations present a number of typical mishaps that can lead to personal injury. Many of these hazards are associated with the forces and energy exerted by the pump and should be…
Concrete pumping operations present a number of typical mishaps that can lead to personal injury. Many of these hazards are associated with the forces and energy exerted by the pump and should be…